Newcastle City Construction Update Monday 6 to Sunday 12 November 2017

To read this week's city centre  construction summary click on the link below.

Newcastle City Construction Update: Monday 6 to Sunday 12 November (PDF 230kb)

Highlights for the week ahead include:

Supercars

  • This week will see the installation of temporary fencing across multiple locations. 
  • Barrier installation will commence in Watt St from Monday 6 November
    - Starting with: Watt Street – Scott to Hunter (approx. 2 days)
    - Followed by: Watt Street – Hunter to King (approx. 2 days)
    - Finishing with: Watt Street – King to Church (approx. 2 days)
Newcastle Light Rail
  • Work in Zone 6, Hunter Street between Crown Street and Perkins Street has started.
  • 30 angled 2-hour parking spaces will be temporarily created on the southern side of Hunter Street between Darby and Crown streets.

 